Hydroelectricity plant in Rościno

Energy works on modernisation of the Rościno hydroelectricity plant on the Parsęta river in their initial phase consisted in placing transformers and cable lines connecting the MV switchgears 15kV with electric power generators. The following phases comprised of the installations of: supervision of the building, measurement points of the amount of green energy produced by optic connections, heating of the cheek sheets and control of the weir traps. The last phase comprised of installing lighting, emergency aggregate, switchboards of emergency direct current power and remaining installations required for maintenance-free work of the plant.

The electric installation is an interesting element of the investment, as it is located in a tunnel running under the riverbed (adit). It supplies six hydraulic aggregates that move the hydrotechnical sliders.