In the initial phase, energy works related to the modernization of the Rościno hydroelectric power plant on the Parsęta River consisted of installing transformers and laying cable lines connecting MV-15kV switchgears with power generators.
W kolejnych fazach wykonano instalację: nadzoru obiektu, pomiaru wyprodukowanej energii zielonej poprzez połączenia światłowodowe, ogrzewania blach policzkowych oraz sterowania klapami jazu.
The last elements of the construction were the connection of lighting, an emergency generator, DC emergency power switchboards and the remaining installation required for maintenance-free operation of the power plant.
An interesting element of the investment is the electrical installation, which is located in a tunnel running under the river bed (adit). It supplies power to six hydraulic units that move the hydraulic shutters.