Hydroelectric power plant in Rościn

The energy works related to the modernization of the Rościno hydroelectric power plant on the Parsęta river consisted in the initial phase of inserting transformers and laying cable lines connecting the SN-15kV switchgears with power generators.

In the next phases, the installation was completed: facility supervision, measurement of green energy produced through fiber optic connections, heating of cheek sheets and control of weir flaps.

The last elements of the construction were connecting lighting, emergency aggregate, DC emergency switchboards and other installation required for unattended operation of the power plant.

An interesting element of the investment is the electrical installation, which is located in the tunnel under the riverbed (adit). It supplies six hydraulic aggregates that move hydrotechnical valves.